Botad Bridge Collapse (June 2025): A three-year-old bridge over the Patalia River was washed away due to heavy rainfall.
Bullet Train Structure Collapse – Anand (5 November 2024): A temporary structure for the Mumbai-Ahmedabad bullet train project collapsed over the Mahi River, killing three workers and injuring one. The incident raised serious concerns about the safety standards of India’s first high-speed rail project.
Bodeli-Chhota Udepur Bridge (28 August 2024): A bridge connecting Bodeli and Chhota Udepur gave way after intense rainfall.
Chotila Bridge Collapse (27 August 2024): A bridge near Hubiasar village in Surendranagar’s Chotila taluka collapsed amid heavy rain, cutting off access to over five villages.
Halvad Bridge Collapse – Morbi (26 August 2024): A year-old bridge in Halvad, Morbi district, was destroyed by torrential rains.
Surat Metro Flyover Sags (30 July 2024): A section of a metro flyover in Saroli, Surat, sagged before its inauguration, with visible cracks in the bridge slab.
Ambedkar Bridge Partial Collapse – Mehsana (14 February 2024): A section of the Ambedkar Bridge caved in unexpectedly.
Palanpur Overbridge Collapse (23 October 2023): Part of an under-construction overbridge near the RTO circle collapsed, killing one and injuring others.
Kheda Bridge Collapse (4 October 2023): A bridge connecting Pariej and Baman villages in Kheda district fell into a canal.
Dhandhusar Bridge Collapse – Junagadh (5 July 2023): A 45-year-old bridge over the Uben River collapsed, cutting off 20 villages from Junagadh.
Morbi Suspension Bridge Tragedy (30 October 2022): The Machchhu river suspension bridge collapsed just four days after reopening, killing at least 141 people. No one has yet been held accountable.
Madhapar Chokdi Bridge Incident – Rajkot (25 January 2022): A concrete cap collapsed during construction of a bridge on Rajkot’s Ring Road, injuring two laborers.
Mumatpura Bridge Span Collapse – Ahmedabad (21 December 2021): A span of the Mumatpura bridge gave way unexpectedly.
Hatkeshwar Bridge – Ahmedabad (2021–22): Built in 2017 at a cost of ₹40 crore, the bridge was declared unsafe within four years, leading to a demolition tender.
Mehsana Bypass Bridge Bend (24 January 2020): A bridge over the Khari River developed a visible bend just six years after construction.
Ajidam Chokdi Bridge Collapse – Rajkot (2020): A bridge near Ajidam Chokdi failed structurally.
Piplod Flyover Collapse – Surat (2019): The flyover suffered a major structural failure, adding to the list of infrastructure mishaps in the city.